The former global headquarters of The Dow Chemical Co. in Midland, Michigan, collapsed unexpectedly while a portion of it was being demolished, a report by mlive.com says. No one was injured from the collapse.
Three stories of a corner of the building collapsed on top of one another at around 8:15 a.m. May 24. Jerrod Erpelding, spokesperson for Dow, says in the report the collapsed was caused by a weakening in the structure as part of the demolition project. An emergency response team is currently on-site to ensure safety and job site management.
The Midland Fire Department sent two engines, a rescue truck and a battalion chief to the scene after receiving a call from Dow. The report says the department stayed at the site for 20 minutes to ensure everyone involved was safe and there were no hazards.
Dow had already completed necessary asbestos abatement procedures prior to demolition.
The report says the company completed construction of its new six-story, 184,000-square-foot Global Dow Center in July 2017.
Latest from Construction & Demolition Recycling
- Waste Pro files brief supporting pause of FMCSA CDL eligibility rule
- Des Moines project utilizes recycled wind turbine blades
- Vecoplan to present modular solutions at IFAT 2026
- Terex Ecotec appoints Bradley Equipment as Texas distributor
- Greenwave raises revenue but loses money in Q2 2025
- Recycled steel prices hold steady
- John Deere launches ‘Building America’ excavator contest
- Triumvirate Environmental acquires Environmental Waste Minimization